Nghiên cứu xác định thời gian thi công công trình ngầm bằng máy đào hẩm loại nhỏ có xét ảnh hưởng của sự cố

- Tác giả: Đặng Trung Thành
Cơ quan:
Trường Đại học Mỏ - Địa chất
- Từ khóa: module mô phỏng, các sự cố, mô hình hóa, hệ thống SysML, phần mềm AnyLogic
- Nhận bài: 08-11-2015
- Chấp nhận: 12-10-2016
- Ngày đăng: 31-12-2016
- Lĩnh vực: Xây dựng Công trình ngầm và Mỏ
Tóm tắt:
In last 20 years, there are more than 1000 Micro Tunnel Boring Machines (MTBM) has been used for tunnel constructions with small crosssection. There are a lot of projects used MTBM’s frequently do not reach their targeted production performance. Reasons can be technical failures, insufficient capacity dimensioning, organizational deficiencies, or sensitive supply chains, some technical problems is occurred in the process of construction. One year in order to fix the disturbances at project in Nhiêu Lộc-Thị Nghè canal is a typical example. The time to finsh the project is important information that investors as well as contractor need to make the decisions during construction process, Therefore, the MiSAS module combined with the empirical formula is used in the paper for predicting the construction time of tunnel with MTBM considering the effects of the disturbances. Moreover, two actual projects at the city of Recklinghausen, Germany, is used for the study case.

1. Dang, T. T., 2013. Analysis of microtunnelling construction operations using process simulation. Dissertation, Ruhr-Universität Bochum, Fakultät für Bau und Umweltingenieurwissenschaften, Shaker Verlag, ISBN 978-3-8440-2454-8.
2. Marzouk, M., M. Abdallah, and M. Ei-Said,, 2010. Modelling microtunnel ling projects using computer simulation. Journal of Construction Engineering and Management 136(6), 670-682,
3. Mohamed, Y. H. and R. s. Gary (2007). Delay time analysis in microtunneling projects. Journal of Construction Engineering and Management 133(2), 191-195. " '
4. Nido, A. A., C. J. Knies, and D. M. Abraham., 1999. Role of operation simulation in the analysis and improvement of microtunnelling projects. Tunneling and Underground Space Technology 14(1), 1-19.
5. Roy, Y. L. and N. Mohammad., 2007. Productivity study of microtunneling pipe installation using Simulation. Journal of Infrastructure Systems 13(3), 247-260.
Các bài báo khác